jreid
01-23-2005, 06:15 PM
I am moving my water meter in my basement, increasing the size of the main trunk from 1/2" to 1" and relocating the water meter (in the basement). I want to do this because
1. The water main comes in through the floor about 16 inches from the wall and I am trying to finish the basement. I WILL NOT box around the thing. I have thought about this and it would be impractical and obtrusive.
2. The main comes in as 3/4" and reduces to 1/2" after the meter, check valve and 2nd shut off.
3. The main trunk is 1/2" pipe for a 3000 sq. ft. house. I am making it 1". The plumber that did this should be drawn and quartered. If someone turns a faucet on while you're in the shower, the pressure drops to a trickle.
This is what I know
1. The meter must be relocated since it must be mounted horizontal, face-up and the face must be readable.
2. I cannot make a solder connection to the main pipe.
My current plan is to relocate the meter to what will be a closet and drop it down about 16" so that it can be accessed and read easily. I've got all the details with that worked out.
My problem is the connection to the main. I have busted up the concrete slab in the basement. The pipe is a 3/4" copper pipe that comes through the footer and is bent up to vertical to go through the slab about 16" from the wall. I have removed the slab up to the wall.
I intend to make a connection to the pipe and bury it since it will be below-slab and out about 14" in the middle of the floor.
I need advice. I am assuming since I cannot make a solder connection, I must use a compression fitting to make the connection to the main. I will have to make several turns through several 90 degree fittings to allow me to make a connection back up against the wall. Is there any other way to make this connection that would be simpler and reliable? Why can't a solder connection be used on the main pipe? Do you see any problem with burying the connection below slab after it is made?
Thanks
1. The water main comes in through the floor about 16 inches from the wall and I am trying to finish the basement. I WILL NOT box around the thing. I have thought about this and it would be impractical and obtrusive.
2. The main comes in as 3/4" and reduces to 1/2" after the meter, check valve and 2nd shut off.
3. The main trunk is 1/2" pipe for a 3000 sq. ft. house. I am making it 1". The plumber that did this should be drawn and quartered. If someone turns a faucet on while you're in the shower, the pressure drops to a trickle.
This is what I know
1. The meter must be relocated since it must be mounted horizontal, face-up and the face must be readable.
2. I cannot make a solder connection to the main pipe.
My current plan is to relocate the meter to what will be a closet and drop it down about 16" so that it can be accessed and read easily. I've got all the details with that worked out.
My problem is the connection to the main. I have busted up the concrete slab in the basement. The pipe is a 3/4" copper pipe that comes through the footer and is bent up to vertical to go through the slab about 16" from the wall. I have removed the slab up to the wall.
I intend to make a connection to the pipe and bury it since it will be below-slab and out about 14" in the middle of the floor.
I need advice. I am assuming since I cannot make a solder connection, I must use a compression fitting to make the connection to the main. I will have to make several turns through several 90 degree fittings to allow me to make a connection back up against the wall. Is there any other way to make this connection that would be simpler and reliable? Why can't a solder connection be used on the main pipe? Do you see any problem with burying the connection below slab after it is made?
Thanks