mrhayne
04-26-2005, 08:56 AM
I have removed the old front porch which was about 4' by 20'. It was attacjed to the hose with reb bar and bricks were removed and the concrete was poured into the voids left by the brick. The slab also used to support the roof above. It no longer needs to souport the roof. I would like to repour a new slab. Here is my question. Can I trench and pour a frost wall with out footings? Could I pour the frost wall first and then pour the slab later or do they need to be done in a monolithic fashion. I am concerned the the trench for the frost wall will not hold with the forms for the top slab??