Old 10-29-2009, 06:40 PM   #1
NJDAVE
Newbie
 
Join Date: Oct 2009
Location: New Jersey
Posts: 3
Default Unlevel floor

My first floor sags in the middle by about an inch in some places. The consensus of a few contractors and structural engineers is that the web/truss joists supporting the floor were either undersized or perhaps got wet during construction. In any case, the joists have deflected in the middle.

All of the contractors said their solution would be to put two posts down the center of my finished basement and connect a 12" girder between them. I have balked at this because it would destroy the basement which is a nice open room.

The alternative which no one wants to touch is to tear up the first floor and basement ceiling and then sister the existing joists with level ones. This would require cuttiing the plumbing and electrical that is threaded through the joists. No one I have talked with wants to do this. I am not sure why. Can someone clue me in? Thanks
NJDAVE is offline   Reply With Quote
Old 10-29-2009, 08:38 PM   #2
RTF
Developer
 
Join Date: Sep 2009
Location: Atlanta, GA
Posts: 104
Default

It would be an absolute nightmare to attempt what you have suggested. Take the contractors' advice and install the posts and beam. There is a lot more to it than moving plumbing and electrical, your exterior walls sit on top of your floor system. If you start removing them you will compromise the integrity of your structure.
RTF is offline   Reply With Quote
Old 10-30-2009, 12:45 AM   #3
Joe Carola
Veteran Member
 
Join Date: Sep 2004
Location: New Jersey
Posts: 367
Default

Quote:
Originally Posted by NJDAVE View Post
My first floor sags in the middle by about an inch in some places. The consensus of a few contractors and structural engineers is that the web/truss joists supporting the floor were either undersized or perhaps got wet during construction. In any case, the joists have deflected in the middle.

All of the contractors said their solution would be to put two posts down the center of my finished basement and connect a 12" girder between them. I have balked at this because it would destroy the basement which is a nice open room.

The alternative which no one wants to touch is to tear up the first floor and basement ceiling and then sister the existing joists with level ones. This would require cuttiing the plumbing and electrical that is threaded through the joists. No one I have talked with wants to do this. I am not sure why. Can someone clue me in? Thanks
How old is this house? Is this a house you had built, or did you buy this house from a previous owner?
__________________
Joe Carola
Joe Carola is offline   Reply With Quote
Old 11-04-2009, 01:08 PM   #4
NJDAVE
Newbie
 
Join Date: Oct 2009
Location: New Jersey
Posts: 3
Default Unlevel floors

Quote:
Originally Posted by Joe Carola View Post
How old is this house? Is this a house you had built, or did you buy this house from a previous owner?
The house was built in 1986 and I bought it from a previous owner.
NJDAVE is offline   Reply With Quote
Old 11-04-2009, 06:03 PM   #5
Don_P
Administrator
Veteran Member
 
Join Date: Mar 2005
Location: Blue Ridge Mts, VA
Posts: 1,110
Default

It is sometimes possible to run threaded rod from the top at each end of each joist, diagonally down to the middle bottom, jack the floor slightly above level and tighten the rods with turnbuckles, essentially bowstringing each joist. This might be worth talking with the engineer about and seeing if it is possible to preserve the basement space.

An engineer should be able to definitively say whether the joists were undersized if they can see one. If they have seen one and cannot make this determination look for another engineer.

Last edited by Don_P; 11-04-2009 at 06:17 PM.
Don_P is offline   Reply With Quote
Old 11-05-2009, 06:25 PM   #6
bighammer
Developer
 
bighammer's Avatar
 
Join Date: Jul 2008
Location: Iowa
Posts: 252
Default

i have done the threaded rod on the roof - Don you are always ontop of your game - good idea and great line about the engineer
__________________
if you can't fix it with a hammer, it must be an electrical problem
bighammer is offline   Reply With Quote
Old 11-07-2009, 08:39 AM   #7
NJDAVE
Newbie
 
Join Date: Oct 2009
Location: New Jersey
Posts: 3
Default

Thanks Don_P. I will see if I can take this approach.

The engineer proposes developing a report that would include a definitive opinion and recommendation. That would cost about $750. The plan itself would be an additional $750 to $1000.

I may first see if I can find a local contractor who has experience with this approach.

Thanks
NJDAVE is offline   Reply With Quote
Reply

Tags
floor, joists, unlevel

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump


All times are GMT -8. The time now is 05:40 PM.

Sub Navigation


Powered by vBulletin® Version 3.8.4
Copyright ©2000 - 2009, Jelsoft Enterprises Ltd.
© 2003-2009 Construction-Resource.com